EOHHS – Order Process / Workflow
- Customer provides blueprints, furniture plan, user counts (and other ancillary information) to TechChoice (Paul Storella).
- Is this NEW or EXISTING (if existing, we need current AP placement)
- TechChoice (Paul Storella) schedules call with EOHHS to review requirements to Windstream AM (Greg Thorsell)
- Address Information
- Contact Information
- Timeframes
- Windstream cabling?
- If SD-WAN
- Circuit types
- Circuit bandwidth
- Circuit carriers
- If NaaS, move to nest step
- TechChoice (Paul Storella) & Windstream AM (Greg Thorsell) confirm and approve technical requirements spreadsheet.
- Windstream AM (Greg Thorsell) sends requirements to Windstream Pro Services (Jesse Hunton).
- Windstream Pro Services (Jesse Hunton) schedules the initial site survey – requires at least 5 business day’s advance scheduling.
- Qty of AP’s
- Qty of Cable Runs
- Length
- Difficulty
- Any additional IDF needs?
- Any additional LAN requirements
- Windstream Pro Services (Jesse Hunton) create a Professional Services Quote.
Includes
- Heat Map identifying qty and placement of AP’s
- Statement of Work for cabling and LAN Requirements
- Windstream AM (Greg Thorsell) send Heat Map and Plan to TechChoice (Paul Storella).
- TechChoice (Paul Storella) & Windstream AM (Greg Thorsell) & Windstream PM (Andrew Farnan) review Project with EOHHS for approval.
- Heat Map
- SOW
- Technical Requirements (including cables)
- Timeframes
- EOHHS approves project to move forward
- Windstream AM (Greg Thorsell) creates the Windstream Quote & CNS Form.
- Windstream AM (Greg Thorsell) sends CNS Form to TechChoice (Paul Storella).
- TechChoice (Paul Storella) sends CNS to EOHHS IT Contact (Jeff Martineau) via DocuSign for 1st approval.
- TechChoice (Paul Storella) sends CNS to EOHHS site contact for signature via DocuSign.
- TechChoice (Paul Storella) & Windstream AM (Greg Thorsell) receive signed DocuSign CNS from EOHHS.
- Windstream AM (Greg Thorsell) submits the order in WinForce.
- Windstream Project Manager (Andrew Farnan) assigned.
- Confirm implementation timeline – Network connectivity is ordered
- Materials are ordered, network connection is installed/verified, and technician scheduled.
- Implementation / Activation Scheduled
- Work includes AP placement, switch installation, any additional cabling if approved, and service activation with Windstream SAT team
- Burn-in and end user confirmation
- 60-90 days in identify any gaps in coverage and understand if that is due to AP placement, or need for an additional AP’s.